Audubon Hospital Facility Master Plan - Norton Healthcare
Louisville, KY
Features
- Throughout the construction of all five projects, the project team maintained high levels of communication with the hospital so it could remain operational 24/7/365. This was accomplished through phasing solutions and successfully implementing our 5S safety components as part of our Zero Injury culture.
- A four-story parking garage was constructed at the same time as expanding the emergency department by 50%. This efficiency to the project saved 18 months on the schedule.
- The emergency department remained fully operational during its expansion and during the new bed tower construction. Through creative phasing, the hospital maintained its census and had no drops in their Q scores.